Weather permitting, work is scheduled to begin May 13 on N-50 north of Pawnee City,

Reference Post 13.66 to 16.39, according to the Nebraska Department of Roads.

Weather permitting, work is scheduled to begin May 13 on N-50 north of Pawnee City,

Reference Post 13.66 to 16.39, according to the Nebraska Department of Roads.

            Constructors, Inc. of Lincoln, Nebraska has the $969,217 contract to mill and resurface

this 2.7 mile project.  Traffic will be controlled by one-lane work zones and flaggers where

necessary.  The project is expected to be completed in June 2013.

            The Department of Roads’ project manager is Bill Cary of Tecumseh.  Motorists are

reminded to drive cautiously through construction zones.